Balancing air/water (with discovery)
1 | Create an ABT Site project. | |
2 | Set up the connection to the device. | |
3 | Connect the laptop to the automation station. | |
4 | Open Startup > Global functions. | |
5 | Issue Global commands: --Select parameters --Select engineered or discovered automation stations. | |
6 | Balance automation stations: --Select an automation station and Go to web interface. --Follow procedure for air or water balancing |
|
7 | Release Global commands. | |
8 | Repeat steps 4 through 6 for all automation stations. |
|
9 | Update online report data. | |
10 | Create a report. | Reports |
11 | Open Startup > Export. | |
12 | Create Pack & Return file. | |
13 | Handover following data to project owner (optional) -- Pack & Return file (*.ABTReturn) |
|
Possible next step: complete an ABT project.